Building Update - September

Progress on our purpose-built school site is well underway and we can now see the building starting to come to life. The roof is now on and the external walls are 90% complete, the internal walls are currently being installed so we can now see the internal layout and the size of each room. Our new school will have a dance studio, school hall and similarly to Wellington Primary Academy, our EYFS and KS1 classrooms will be on the ground floor with KS2 on the first floor. We will also have our nursery, Eagles Nest, inside the building which is a bit different to our current Nest Nursery which is next door to Wellington Primary.

Our fantastic builders, Bray & Slaughter are also currently working on installing windows and doors so we will be weatherproof in time for the chilly and rainy British winter!

The next stage is to finishing cladding the outside of the building and begin the fit out the inside. We are excited to share the next update!